DIMO was contracted for the the Kilinochchi Water Supply Scheme project funded by the World Bank, with the National Water Supply and Drainage Board (NWSDB) as end-use.
This national project is implemented by the Water Supply & Sanitation Improvement Project (WASIM). DIMO was able to construct a fully-fledged water treatment plant in Kilinochchi with a total capacity of 4,500 m3 a day. It comprises of an underground sump and sand filtration, with axillary equipment, yard pumping and generator house.
The plant uses a newer technology – Dissolved Air Flocculation. Catering to about 1000-1500 households, this is the largest treatment plant constructed by DIMO thus far.