| Client |
Type Of Project |
| British High Commission |
Design, Supply,Installation,testing and Commissioning of a state of the art Building Management System that integrates all the services in the building. This is the new building for British High Commission in Sri Lanka |
| Orion Development (Pvt) Ltd. |
Design, Supply,Installation,testing and Commissioning of Addressable Fire Detection, Sprinkler , Hose Reel & Building Management system. This is the phase I of a large IT Complex being developed by Orion Development. The Phase1 building is uccupied by Vertusa. |
| Fair Mount Residencies |
Supply,Installation,testing and Commissioning of fire detection & protection system. This is a Super Luxury Apartment Building of 30 Storied. |
| Ceylinco Health Care Centre |
Supply,Installation,testing and Commissioning of Advance, addressable fire detection & protection system |
| Dialog Telekom (Ltd).475,union Place Colombo-2 |
Supply,Installation,testing and Commissioning of FM-200 Fire Suppression Systems For 10 Nos of base Stations located at variouse cities. |
| Aitken Spence |
Design, Supply,Installation,testing and Commissioning of a comprehensive Building Management System that integrates all the services in the building. The System has the ability to bill for Air Conditioning as per usage by each floor and the proposed BMS controls the lighting system of the building. Expected Energy Saving is 25%. This is the new building for Corporate office of Aitken Spence. |
| ICC Housing |
HT Works at Iceland residencies Project including 1500KVA Transformers and Vacuum Circuit Breakers with associated equipments. This is a Luxury Apartrment Building developed bu ICC - 32 storied |
| St Anthony's Group |
Supply & Installation of 2x2000KVA Transformer and Vacuum Circuit Breakers with out Door Switch yard. |
| Pyramid Lanka |
Supply & installation of 2000KVA,ONAN,On-load Tapped Transformers 2 Nos and SF 6 Circuit Breakers 3 Nos |
| Sri Lanka Telecom (Ltd) Paliyagoda warehouse |
Supply,Installation,testing and Commissioning of Addressable Fire detection, CCTV and lighting System . |
British Council
Sri Lanka. |
Supply,Installation,testing and Commissioning of Intelligent addressable Fire Detection & Alarm system |
| Ceylon Electricity Board |
Sapugaskanda Diesel power plant(4x10MWx2) Extension of 11KV and 132KV Electrical Installation Works(132/33KV GIS, Switch Gear,132KV AIS Switch Yard) |
| NWS & DB |
Automatic, Low Voltage 3000 KNAR Capacitor Bank Project At Ambathale Intake |
| Holcim Lanka Puttalam |
33KV GIS Substation Project |
| Holcim Lanka Puttalam |
Automation and Electrical Rehabilitation project (11/33 KV AIS/GIS &33/0.4KV) Transformers |
Bank of Ceylon
(Merchant Tower) |
(11/0.4 KV 2x800KVA Siemens cast resin transformer,11KV 800A 20KA Siemens Switchgear panels and 110V Dc power supply system) |
Bank of Ceylon
(Merchant Tower) |
Supply, installation, testing & commissioning of 11/0.4KV,2x800KVA SIEMENS Cast Resin Transformers,11KV,800V,20KA/3Sec SIEMENS Switch Boards and 110 V DC Battery Bank with charger system |
| Development Holdings Ltd. (NDB Tower) |
1/0.4 KV 2500KVA Siemens Oil sealed transformer,11KV 800A 20KA/3Sec Siemens Switchgear panels and 110V Dc power supply system |
Development Holdings Ltd
(NDB Tower) |
Supply installation testing & commissioning of 11/0.4KVA SIEMENS Oil Sealed Transformers,11KV,800A, @)KA SIEMENS SWITCH Boards 110V DC Battery Bank with charger system at NDB Tower |
| Ceylinco Seylan Tower |
11/0.4 KV 2500KVA Siemens cast resin transformer,11KV 800A 20KA/3Sec Siemens Switchgear panels and 110V DC power supply system |
Nestle Lanka
Pannala |
Electrical Rehabilitation Project (11KV,3.3 KV) |
South Access
Gateway Terminal |
Access control system for SAG project |
Load Star Limited
(Jinasena Group) |
11KV 800A 20 KA Siemens Switchgear panels |
| Asian Hotels & Properties Limited |
Supply, installation, testing & commissioning of 11/0.4KV,3x800KVA ELMKE Cast Resin Transformers at Crescat Development Building |
| Ansell Lanka |
33KV GIS Substation Project |
| Crescat Development Building |
11/0.4 KV 3x800KVA Helmke cast resin transformers |
| JAIC Hilton Tower |
(11KV 800A 20 KA Siemens Switchgear panels) |
| Ceylon Electricity Board |
Siemens with Dimo have secured a large Power Sector Project and the work is now in progress. This includes building of two switch yards for the proposed 300MWpower plant at Kereawalapitiya. |